Construction has again moved along at a nice pace in the past two weeks. In the clinic, workers finished pouring all concrete beams, which means the roof is up next! Tomorrow, Lord-willing, the carpenters will start the formwork for the roof, which should take a couple weeks. We recently stocked up on bamboo to use as supports for the formwork (50 dozen, to be exact).

 

 

Carpenters Prepare Beam Formwork

 

 

Iron Workers Place Rebar for Beams

 

 

Bamboo for Roof Formwork

 

 

Clinic as of 10/6

 

 

The pharmacy has also changed quite a bit in the past two weeks. The foundation is now complete up to ground level, and while the carpenters are working on the roof formwork for the clinic in the next couples weeks, the masons will be able to finish placing rock for the pharmacy foundation and then pour the concrete floor. Let’s pray for a drier-than-usual rainy season!

 

Carpenter

 

 

Pouring Concrete for Pharmacy Foundation

Please reload

© 2016 by Friends for Health in Haiti, Inc., a 501(c)3 non-profit organization registered in Wisconsin.

OFFICIAL LINKS

  • Facebook Clean
  • wplogo2.png